{"id":10478,"date":"2012-11-09T16:12:17","date_gmt":"2012-11-09T21:12:17","guid":{"rendered":"http:\/\/www.montclair.edu\/news\/article.php?ArticleID=10478"},"modified":"2018-05-08T11:55:19","modified_gmt":"2018-05-08T15:55:19","slug":"10478_construction-update-for-week-of-november-12","status":"publish","type":"post","link":"https:\/\/www.montclair.edu\/facilities\/2012\/11\/09\/10478_construction-update-for-week-of-november-12\/","title":{"rendered":"Construction Update for Week of November 12"},"content":{"rendered":"

Construction is ongoing for the new combined heating, cooling, and power (CHCP) plant next to CarParc Diem. All steel beams are now in place and the installation of precast concrete panels will begin shortly. If you visit the site, you will notice that the natural gas-fired turbine electric generator is now in place under the wooden crate-like structure and next to it under sheet plastic is the heat recovery steam generator whose energy will be used to heat and cool the campus. Please be aware of the following:<\/p>\n